Framing Layout & Design

Spacing, rough openings, headers, and spans — the numbers that decide everything downstream.

Stud & wall specs

Exterior walls
2x4 or 2x6 @ 16" O.C. — use 2x6 for plumbing walls and extra insulation
Interior non-bearing
2x4 @ 16" O.C. (24" O.C. acceptable for non-bearing in some codes)
Plumbing walls
2x6 minimum — shower valves and toilet flanges need the depth
Corners / intersections
California corner or ladder backing so both faces can be nailed and insulated

Rough opening rules

Interior door
R.O. width = door width + 2"; height = door height + 2½" (slab) or + 3½" (over finished floor w/ carpet & pad)
Pre-hung door
Use the door unit's listed R.O. — typically width + ½" to 1", height + 1½" to 2"
Window
Use manufacturer's R.O. exactly — check every unit; R.O.s vary between brands
Shower / tub alcove
Framing plumb and true to the fixture spec — tubs and pans are unforgiving; ½" out of square shows in every tile joint
Curbless shower
Recess or slope the subfloor early — planning for it after framing costs triple

Header sizing (rule of thumb)

Floor joist spans @ 16\" O.C.

2x816" O.C.≈ 12' – 13'
2x1016" O.C.≈ 15' – 16'
2x1216" O.C.≈ 18' – 19'
I-joist / floor trusses19.2" or 24" O.C.Per manufacturer chart — always confirm with the span tables for your species/grade

Confirm against your species/grade span tables — these are guides, not a substitute for the code book.

Layout tips from the field

  • Snap plate lines on chalk lines — keep exterior corners square by measuring diagonals before you nail anything.
  • Layout doors away from corner jog; leave room for trim casings (usually 3" min from a corner).
  • Nail blocking mid-wall for chair rail, grab bars, TV mounts, and towel bars — cheap now, impossible later.
  • Dry-lay bathroom walls early: valve depth, toilet flange (12" from finished wall), and curb height all get decided here.
  • Fire-block every furred chase and soffit penetrations between living space and attic.

Rough-In & Trim-Out Heights

Standard placement heights — verify against local code and appliance spec sheets.

ItemStandard height / ruleNotes
Wall receptacle12" to box top (12"–16" typical)Max 12' between receptacles on a wall run; any wall 24"+ needs one
Countertop receptacle~44" / 3"–4" above backsplashGFCI required; first within 2' of sink edge; one every 4' of counter
Switches48" to top (48"–52")On the latch side of the door; keep consistent room to room
Thermostat52"–60"Interior wall, away from direct sunlight, supply vents, and kitchen heat
PanelTop of panel ≤ 6'7"36" wide x 30" deep clear working space in front, always
Smoke detectorCeiling (4" from wall) or 4"–12" below ceiling on wallEvery bedroom, outside each sleeping area, one per level minimum; interconnected
Water heater disconnectWithin sight, eye levelNon-fused disconnect or breaker lock for electric units
Dryer / range outletsPer appliance specs (often 4"–12" behind unit)4-wire on new builds; check cord vs outlet match at trim-out
Exterior receptacles≥ 12"–16" above grade, in-use coversFront & rear of dwelling required; GFCI protected
Doorbell48"Transformer on a dedicated accessible junction

Shower Installation

Frame to trim-out, in order — water management first, tile second.

Pre-slope, weep holes, flood test, silicone. The #1 shower callback is water management, not tile — pre-slope, weep holes, flood test, and silicone at every change of plane.

  1. 1

    Frame & prep

    Curb at 4½"–5", blocking at 33"–36" for grab bars and benches, and a 2x10 or open stud bay where the valve goes. Dry-set the pan and check level both ways before anything is permanent.

  2. 2

    Rough plumbing

    Valve at 42" centered, shower head stub at 80". Pressure-test the valve before closing the wall — a failed solder joint behind cement board is a full tear-out.

  3. 3

    Pan & liner

    Pre-slope the subfloor at ¼" per foot to the drain before the liner goes down. Clamp the liner over the pre-slope, run it up the studs 6"–8" and over the curb in one piece, and keep the weep holes open with washed gravel.

  4. 4

    Curb & dam corners

    Use preformed dam corners at the curb ends — folding the liner there by hand almost always leaks.

  5. 5

    Backer board

    Cement board or foam board nailed to the flange line, with a ¼"–½" gap above the pan. Tape and mortar the seams. Never use drywall in a wet zone.

  6. 6

    Waterproof

    Two to three coats of liquid membrane (paint the seams, fasteners, and curb twice) or a fabric system. Flood-test the pan 24–72 hours before tile — this is the single step that saves callbacks.

  7. 7

    Tile & grout

    Floor tile pitches to the drain. Keep grout joints in wet floors at ⅛"–¼" sanded. Never grout the change-of-plane joints (pan-to-wall, corner-to-corner) — those get 100% silicone.

  8. 8

    Trim out

    Install the finish trim, seal plane changes and fixtures with silicone (match the grout color), and run the shower full-flow for 5 minutes watching the ceiling below.

Tile & Flooring Finish Work

Prep, layout, joints, and transitions — the details that separate a show job from a callback.

Subfloor & prep

  • Tile floors need deflection of L/720 in wet areas (stiff, not just strong) — add blocking or a second layer before you blame the mortar.
  • Substrate must be flat within ⅛" per 10 feet — self-level or mud it. Flatness failures cause more cracked tile than anything else.
  • ¾" T&G subfloor + cement board (mortared and screwed) or an uncoupling membrane for standard installs.

Layout

  • Dry-lay and snap control lines from the room's main sightline (usually the entry) — don't start from a corner.
  • Large-format tile (16"+): use a ⅓ offset pattern, not 50%, and an anti-lippage system.
  • Undercut door jambs and casings so tile slips underneath — cuts at the casing always show.

Grout & joints

  • Rectified tile: ⅛" joints are fine. Standard edge tile: ¼"–⅜". Never butt joints.
  • Sanded grout for floors and joints over ⅛"; unsanded for walls and thin joints.
  • Seal cementitious grout after full cure; caulk (not grout) every plane change.

LVP & wood-look flooring

  • Acclimate 48 hours in the room; check slabs for moisture before floating anything.
  • ¼" expansion gap at all walls and verticals — LVP needs to move; use T-molding over 30–40 ft runs.
  • Stagger end joints 6"–8" apart and never repeat the same plank sequence — patterns are visible.
  • 1/8"–3mm underlayment over wood subfloors; check the LVP brand — some have it attached.

Transitions

  • Match heights before you pour: tile, mud bed, and LVP stack to different finished floor heights — plan the transition strips before install.
  • Schluter-type edge profiles for tile-to-LVP and tile-to-carpet; T-strips for equal heights.
  • In bathrooms, keep tile higher than LVP run-off — never let water shed onto a floating floor.

What to Include in the Bid

Line-item checklists per trade — drop these straight into a customer bid so nothing gets missed.

Framing package

  • Plan review & permit fees
  • Lumber + engineered lumber takeoff
  • Layout, snap lines, plate walls
  • Frame floors, walls, roof
  • Headers, beams, posts, hardware
  • Sheathing & house wrap
  • Backer/blocking for future fixtures
  • Waste haul & clean-up

Tile & flooring

  • Demo & haul-off of old floor
  • Subfloor prep / flatness correction
  • Backer board or uncoupling membrane
  • Waterproofing (wet areas)
  • Tile labor per square foot + trim pieces
  • Grout, transition strips, thresholds
  • Grout sealing

Shower install

  • Demo to studs & inspection
  • Valve rough-in & pressure test
  • Pan, liner, curb, dam corners
  • Waterproofing + flood test
  • Wall tile, bench, niche
  • Glass door/panel (often separate line)
  • Fixture trim & silicone

Plumbing trim-out

  • Angle stops at every fixture
  • Toilet, vanities, faucets set
  • Shower/tub trim installed
  • Water heater hook-up + T&P discharge
  • Fixture testing under full flow

Electrical trim-out

  • Devices, switches, plates
  • Lighting & ceiling fans
  • Panel breakers labeled
  • Smoke/CO detectors set
  • GFCI/AFCI test & punch walk
Always verify heights and spans against local code and manufacturer specs — these are field standards, not a code book.